How to use. Every heading below is a SOW 4.6.2 requirement, and each asks for
this week and cumulative — that wording is in the SOW, so both columns must be filled.
Type into the blue fields and hit Save as PDF. Nothing is stored on a server.
This report does double duty: clause 26.2(b)(v) requires a program status report with every
progress claim — the latest weekly report, with section 6 completed, is what satisfies it.
1 · Works carried out — SOW 4.6.2
| This week | Cumulative to date |
|
|
2 · Works planned for next week — SOW 4.6.2
3 · Issues — SOW 4.6.2
| Raised this week | Open / carried forward |
|
|
Watch: anything here that delays Completion may need a
Claim for Extension of Time (Schedule 8 form, p.5) — an EOT has notice requirements, so raise it in the
week it happens, not at the end.
4 · Technical queries & other technical items — SOW 4.6.2
| TQ ref | Date raised |
Description | Awaiting | Status |
Watch: a technical query that changes the scope is a Variation, not a query —
it needs a Variation Notice / Variation Quotation (Schedule 8, pp.16–17) before the work is done.
Variation work executed must also be shown separately in the next progress claim (cl. 26.2(b)(ii)).
5 · EH&S issues and statistics — SOW 4.6.2
| Statistic | This week | Cumulative |
6 · Resources on site & diesel used — SOW 4.6.2
| Personnel on site | This week | Cumulative |
| Plant, equipment & consumables | This week | Cumulative |
7 · Progress summary — supports cl. 26.2(b)(v) with each progress claim
| Schedule 3 section | % complete — last week |
% complete — this week | Comment |
8 · Sign-off
Filing. Save the completed PDF to
02 Active Projects\DTL-PRJ0072…\06 Site Documentation\02 Progress Reports.
Keep the weekly reports complete and consecutive — they are the contemporaneous record that supports
progress claims, any Extension of Time claim, and the final account.
DTL (WA) Pty Ltd · ABN 45 677 646 454 · Shark Bay Bitterns Recycling · Commercial-in-confidence
Template built to SOW 23092-SOW-024rD §4.6.2 · 15 Jul 2026